Cogswell ribbon cuttingThis 45,000 sf design-build project for one of the premiere accredited poly-technical colleges had some of the most extreme time constraints Technical Builders has faced. The project consisted of 18 classrooms, student breakroom, 15 offices, a conference room, three collaboration rooms, site work, structural seismic upgrades, Title 24 upgrades, exterior painting, overcoat/re-striping of the parking lot, exterior and interior ADA compliance and bathroom upgrades. Construction was completed in just 6 weeks; fall classes started on time.